Past Projects

BSel Tiling have successfully completed contracts in a number of different sectors from rail to hospitality. Health, Safety, Quality and Environment (HSQE), programme, customer satisfaction and value for money are our key objectives when undertaking projects.

Vauxhall Station

Dates

  • Commenced November 2014
  • Completed May 2016

Works

  • 200m2 of screed
  • 700m2 of Terrazzo floor tiles in ticket hall, cross passages and concourse
  • 300Lm of granolithic skirting installed insitu – not precast
  • 250m2 of ceramic wall tiling
  • 15 floor access hatches and overruling

Client

  • Bechtel Group

Kennington Station

Dates

  • Commenced October 2018
  • Completed April 2019

Works

  • 70m2 of delta lining followed by render at height
  • 80Lm of evaporation channel designed, fabricated and installed
  • 170m2 of riblath followed by render
  • 170m2 of heratige ceramic wall tiling
  • 50Lm of accoustic panelling at height
  • 100 No delta lining and render repairs – track side including provision of access
  • 150m2 of screed to concrete slab
  • 150m2 of concrete pavers
  • 10 access hatches installed and over tiled with concrete pavers
  • 40Lm of render skirting

Client

  • D and D Rail Ltd

 

Bank Station – Bloomberg

Dates

  • Commenced March 2017
  • Completed July 2018

Works

  • 1,200m² of Granazzocem floor tiling over 3 levels
  • Over 100 pre cast stairs with AATi nosing
  • 200Lm of Granazzocem skirting and bevel cut insitu
  • 22no floor access hatches and over-tiled
  • x M2 of x entrance matting
  • 30Lm of tactile pavers at tops and bottoms of stairs

Client

  • Elm Site Services Ltd

St Michaels Rectory

Dates

  • Commenced December 2018
  • Completed January 2019

Works

  • 200m2 of ceramic wall and floor tiling

Client

  • T H Kenyan Plc

Putney High Street Apartments

Dates

  • Commenced December 2018
  • Completed May 2019

Works

  • 400m2 of ceramic tiling with mitered corners to bathroom and shower room walls and floors
  • 35 Niches
  • 25 Shower floors
  • 100m2 quarry tiling to basement areas

Client

  • ARJ Construction Ltd

Finsbury Park Station

Dates

  • Commenced February 2014
  • Competed April 2014

Works

  • Screeded 35m2 of landings
  • Installed 35m2 terrazzo tiles on landings
  • Installed 40 treads and risers
  • Rendered 70m2 of walls and tiled with ceramics

Client

  • Cleshar Contract Services Ltd

Baker Street Station

Dates

  • Commenced May 2014
  • Completed December 2014

Works

  • Patch replaced over 400 terrazzo floor tiles
  • Replaced 60Lm of tactile pavers
  • Supplied tilers managed by client to replace 2000m2 of ceramic wall tiles

Client

  • Cleshar Contract Services Ltd

Kennington Station

Works

  • 70m2 of delta lining followed by render at height
  • 80Lm of evaporation channel designed, fabricated and installed
  • 170m2 of riblath followed by render
  • 170m2 of heratige ceramic wall tiling
  • 50Lm of accoustic panelling at height
  • 100 No delta lining and render repairs – track side including provision of access
  • 150m2 of screed to concrete slab
  • 150m2 of concrete pavers
  • 10 access hatches installed and over tiled with concrete pavers
  • 40Lm of render skirting

Dates

  • Commenced October 2018
  • Completed April 2019

Client

  • D and D Rail Ltd

Putney High Street Apartments

Works

  • 400m2 of ceramic tiling with mitered corners to bathroom and shower room walls and floors
  • 35 Niches
  • 25 Shower floors
  • 100m2 quarry tiling to basement areas

Dates

  • Commenced December 2018
  • Completed May 2019

Client

  • ARJ Construction Ltd

Bank Station – Bloomberg

Works

  • 1,200m² of Granazzocem floor tiling over 3 levels
  • Over 100 pre cast stairs with AATi nosing
  • 200Lm of Granazzocem skirting and bevel cut insitu
  • 22no floor access hatches and over-tiled
  • 30m2 of rubber entrance matting
  • 30Lm of tactile pavers at tops and bottoms of stairs

Dates

  • Commenced March 2017
  • Completed July 2018

Client

  • Elm Site Services Ltd

Towergateway DLR

Works

  • Removed 90m2 of existing ticket hall floor to a minimum depth
  • Leveled 90m2 of substrate with self levelling compound
  • installated 90m2 of Granazzocem floor tiles
  • Installed tactile pavers at the top of escalators

Dates

  • Commenced and completed in July 2016 over 2 weekend closures

Client

  • Marwells UK Ltd

Vauxhall Station

Works

  • 200m2 of screed
  • 700m2 of Terrazzo floor tiles in ticket hall, cross passages and concourse
  • 300Lm of granolithic skirting installed insitu – not precast
  • 250m2 of ceramic wall tiling
  • 15 floor access hatches and overruling

Dates

  • Commenced November 2014
  • Completed May 2016

Client

  • Bechtel Group

Finsbury Park Station

Works

  • Screeded 35m2 of landings
  • Installed 35m2 terrazzo tiles on landings
  • Installed 40 treads and risers
  • Rendered 70m2 of walls and tiled with ceramics

Dates

  • Commenced February 2014
  • Competed April 2014

Client

  • Cleshar Contract Services Ltd

Baker Street Station

Works

  • Patch replaced over 400 terrazzo floor tiles
  • Replaced 60Lm of tactile pavers
  • Supplied tilers managed by client to replace 2000m2 of ceramic wall tiles

Dates

  • Commenced May 2014
  • Completed December 2014

Client

  • Cleshar Contract Services Ltd