Lords Cricket Ground, London

Dates

  • Commenced January 2019
  • Completed May 2019.

Works

  • Installation of access scaffolding for main cleaning works.
  • Cleaning carried out using the DOFF superheated water cleaning method.
  • Dig up existing failed concrete to the low level Mound Stand walkway
  • Clean up substrate prior to installation of new concrete.
  • Supply and install Fosroc Paveroc onto Fosroc Nitobond EP
  • Carryout cleaning of Bas Relief outside of Lord’s Cricket Ground
  • Clean using DOFF superheated cleaning method as approved by English Heritage.
  • Seal stone on completion.

Client

Marylebone Cricket Club